Keeping You Informed
In an ideal world, nothing would break, nothing would need repaired, and everything would look and behave like the day it was installed. But none of us live there. Although we do our best to keep things up and running, there are things just out of our control; and when they are out of our control, it’s hard to communicate all the details of what’s being done, how long until it’s fixed.
This page is a work in progress, but it’s an effort to get real answers to your facility related questions. Expect to find answers on facility updates, upgrades, and repairs … why your favorite treadmill is taking so long to fix, or why the pool seems cold today. You’ll have access to pictures and video of the progress and challenges when available and have the opportunity to let us know what areas need attention and make suggestions for improvement. Updates will be regular and the history of the progress maintained. Projects will fall away after they’ve been resolved. Contact Tom Grantonic, VP Facility Operations with specific questions not addressed here.
Central YMCA Facility Updates
ROOF REPLACEMENT
Boak and Sons will be replacing the roof on the 6th floor in the coming weeks. A waste dumpster and materials chute has been placed in the alley but should not impact any operations or traffic patterns. The old roof was put on in the 90’s and was supposed to last only 5 years. It’s time.

Davis Family YMCA Facility Updates
SHOWERS UNVAVAILABLE – MEN’S LOCKER ROOM
The men’s showers will be unavailable from Sunday, Aug 23 through Tuesday, Aug 25 for some sealing work to be done on the grout. The sealer needs to be applied to a dry surface and remain dry for 24 hrs after the application for proper performance. Showers will be available in the Youth locker room during this time.
OUTDOOR PICKLEBALL COURTS
This spring, weather permitting, two outdoor Pickleball Courts will be constructed in the Davis Outdoor Recreation Area just east of Pavilion 3. This project has been in the works for 2 years getting all balled up in the permit process. Thanks to a generous donation from a friend of the Y, the courts will enable expanded Pickleball opportunities for an ever growing following and provide alternatives when other programming requires the gym space. Watch for constuction to begin as soon as the ground dries out a bit this spring. The project should be ready for use by mid summer.
UPDATE – August 17
Just checked in and they are ready to roll on Monday, assuming the weather cooperates. All the heavy lifting is expected to take a couple weeks. Once the excavation is complete and the asphalt surface laid, it will need to “cure” about 30 days before it can be lined. During this time, crews will be installing fencing and we’ll try and get some landscaping done.
UPDATE – JULY 2, 2026
Site Technology has us scheduled beginning the week of August 24!
UPDATE – May 1, 2026
We had a start date of May 4th for construction to begin, but recent rains is forcing us to postpone the start date a bit. We should be in a better position to pick a new date next week.
UPDATE – June 17
We missed the deadline for starting the project and getting the heavy equipment moved out of there before Day Camp started. All this due to a very wet month of May. Regretfully, the project will have to be pushed to late August. With a little luck, though, there will be an opportunity to get some outdoor play in by late September and into October before the cold weather returns.
LAP POOL CLARITY
LAP POOL CLARITY
Water clarity in the lap pool has been an ongoing problem since the facility opened 20+ years ago. Cosmetics, lotions and body oils contribute to the less than pristine conditions. We partnered with an Aquatics Engineering firm out of Madison Wisconsin about a year ago to determine how to fix it. After thorough study, testing and calulations, it was determined that the pool design and filter flow rates were incorrect based on the capacity and expected bather load. Several recommendations were attempted to see if it made any difference, but none proved successful. While the water chemistry is perfectly fine, the only alternative to improve clarity is to replace the existing filter favoring a higher capacity and flow rate than the existing sand filter.
The filter chosen is a state of the art regenerative filter design that uses perlite instead of sand. The backwash cycle uses a fraction of the water that a typical sand filter uses. In late January, 2026, the Ohio Department of Health approved the design and production of the equipment which is expected to take 6-8 weeks. An installation date will be chose to minimize the impact to class participants, lap swimmers and swim lessons. Cost of this project is approximately $100,000. Here’s a link to learn more.
UPDATE – July 2, 2026
Filter istallation is scheduled beginning August 24
UPDATE – May 1, 2026
Due to a multitude of conflicts with programming, the install of the filter has been delayed until late August when we normally shut down the pools for repair and cleaning.
UPDATE – March 12, 2026
The new filter and related components are officially on site. In an effort to minimize the disruption for swim lessons and other activities, the installation timeframe will be after Labor Day and before Day Camp begins in early June during the time where the outdoor pool is open. We’ll announce more detailed information later this spring. This filter project will cost about $100,000 when all is said and done.
