Keeping You Informed
In an ideal world, nothing would break, nothing would need repaired, and everything would look and behave like the day it was installed. But none of us live there. Although we do our best to keep things up and running, there are things just out of our control; and when they are out of our control, it’s hard to communicate all the details of what’s being done, how long until it’s fixed.
This page is a work in progress, but it’s an effort to get real answers to your facility related questions. Expect to find answers on facility updates, upgrades, and repairs … why your favorite treadmill is taking so long to fix, or why the pool seems cold today. You’ll have access to pictures and video of the progress and challenges when available and have the opportunity to let us know what areas need attention and make suggestions for improvement. Updates will be regular and the history of the progress maintained. Projects will fall away after they’ve been resolved. Contact Tom Grantonic, VP Facility Operations with specific questions not addressed here.
Central YMCA Facility Updates
SAUNA – WOMEN’s LOCKER ROOM
The sauna unit in the women’s locker room at Central is toast. The entire unit has to be replaced and an exact replacement isn’t possible since that particular unit is no longer made. With some careful evaluation, specs for a replacement unit have been identified and a new unit is on order at a cost of about $2000. We should have an update on the ETA within the coming days and will post when we know more.
UPDATE – May 1, 2026
Some wiring issues and misinformation from the manufacturer has delayed the start up of the unit. We thought we had it ready to go, but the updated design created a couple headaches we were unprepared for. Should not be long now that we’ve figured out the problem.
UPDATE – April 7, 2026
Just received word that the new unit will be delivered on Thursday, April 10. We’ll have it installed as early as possible the following week.
ELECTRICAL UPGRADE PROJECT
LOW TEMPS IN FACILITY
Davis Family YMCA Facility Updates
HOT WATER SHORTAGE
PROJECT – HOT WATER ISSUES AGAIN – May 1, 2026
Just a few months after installing a new on demand hot water system to replace two aging 400 gallon traditional tanks, the hardness of Aqua Ohio water is wreaking havoc on the new system causing the heating elements to degrade way faster then anticipated. Right now, one of the two heaters keeps tripping the breaker and we’re running on one. The water is warmish, but not too comfortable on the one unit. New heating elements are being rushed to us for installation, but we don’t have a date.
UPDATE – May 11, 2026
There is still only one unit funtioning, which is not adequate. On Friday, two more elements failed on the one unit. The manufacturers rep was on site this morning working to resolve the problem. Parts are being overnighted today, but can’t be installed until Wednesday. Symptoms indicate that the installed flow meters are not sensitive enough to call for the system to heat when there is not enough hot water demand on the system. That’s what they’re evaluation presently. But there are other questions still to be answered. We’ll keep you informed here as we have updates.
UPDATE – May 8, 2026
Four elements were replaced on May 7 and the system was producing hot water. This morning, there was no water moving through the units. The manfacturer’s rep was contacted and is enroute as of 9 am this morning. We’re praying it a minor hiccup that can be easily resolved, but until he determines what the problem is, we’re without hot water again for the time being.
UPDATE – May 6, 2026
We received some bad intel on the arrival of the parts. It looks like they’re coming today, not yesterday. The manufacturer rep will be at the Y at 9 am on Thursday, May 7 to install.
UPDATE – May 5, 2026
The replacement heater elements have arrived at the manufacturer’s rep’s house today. He’ll be in tomorrow (Wednesday May 6) to install and should have additional information about how to manage the Aqua Ohio water to prevent this from recurring down the road. We’ll be ordering additional elements as backups to keep on hand.
UPDATE – May 1, 2026
To resolve the hard water issue, we’re investigating a couple options… A special filter to remove certain hard water elements or a water softener system in case the filter option isn’t an appropriate solution.
NEW WATER FOUNTAIN INSTALLED
PROJECT – May 1, 2026
A new water fountain has been installed in the fitness center cardio room to replace a problematic one that would only produce a fountain 2” above the fixture. The new one works great! It still maintains the water bottle filler station in the design. Enjoy!

OUTDOOR PICKLEBALL COURTS
This spring, weather permitting, two outdoor Pickleball Courts will be constructed in the Davis Outdoor Recreation Area just east of Pavilion 3. This project has been in the works for 2 years getting all balled up in the permit process. Thanks to a generous donation from a friend of the Y, the courts will enable expanded Pickleball opportunities for an ever growing following and provide alternatives when other programming requires the gym space. Watch for constuction to begin as soon as the ground dries out a bit this spring. The project should be ready for use by mid summer.
UPDATE – May 1, 2026
We had a start date of May 4th for construction to begin, but recent rains is forcing us to postpone the start date a bit. We should be in a better position to pick a new date next week.
LAP POOL CLARITY
LAP POOL CLARITY
Water clarity in the lap pool has been an ongoing problem since the facility opened 20+ years ago. Cosmetics, lotions and body oils contribute to the less than pristine conditions. We partnered with an Aquatics Engineering firm out of Madison Wisconsin about a year ago to determine how to fix it. After thorough study, testing and calulations, it was determined that the pool design and filter flow rates were incorrect based on the capacity and expected bather load. Several recommendations were attempted to see if it made any difference, but none proved successful. While the water chemistry is perfectly fine, the only alternative to improve clarity is to replace the existing filter favoring a higher capacity and flow rate than the existing sand filter.
The filter chosen is a state of the art regenerative filter design that uses perlite instead of sand. The backwash cycle uses a fraction of the water that a typical sand filter uses. In late January, 2026, the Ohio Department of Health approved the design and production of the equipment which is expected to take 6-8 weeks. An installation date will be chose to minimize the impact to class participants, lap swimmers and swim lessons. Cost of this project is approximately $100,000. Here’s a link to learn more.
UPDATE – May 1, 2026
Due to a multitude of conflicts with programming, the install of the filter has been delayed until late August when we normally shut down the pools for repair and cleaning.
UPDATE – March 12, 2026
The new filter and related components are officially on site. In an effort to minimize the disruption for swim lessons and other activities, the installation timeframe will be after Labor Day and before Day Camp begins in early June during the time where the outdoor pool is open. We’ll announce more detailed information later this spring. This filter project will cost about $100,000 when all is said and done.

SHOWERS UNAVAILABLE – MEN’S LOCKER ROOM
PROJECT / SHOWERS UNAVAILABLE – MEN’S LOCKER ROOM
There are about 5 showers that have been taken out of commission that border the steam room wall in the men’s locker room. When the steam room was being renovated, we discovered water seeping in from the shower side that needed to be abated before work could continue. Otherwise, the warranty for the membrane would be voided. Further evalution showed that the water was coming through the basin of the showers and seeping into the room. These showers had to be taken offline before work could continue. The same situation exists on the opposite side, but that water is seeping onto the tile floor underneath the sinks. Youngstown Tile evaluated the project and it was determined that the basins in each of the stalls need replaced. Cost for the renovation is about $55,000. YMCA Trustees approved priority one and two capital projects that includes this one. We will be scheduling the project to begin later this winter. The entire shower area will likely have to be shut down while work is progressing. Stay tuned.
UPDATE – May 1, 2026
This tiling project is nearing completion. The concrete beds have been removed and replaced, a Schulter membrane installed, drains re-worked, tile has been replaced and epoxy grout is currently being placed. The contrasting tile looks like it was designed that way from the beginning. It’s looking great! The grout will have to cure for several days before everything is ready to go, but we’re getting close.

UPDATE – March 30, 2026
On Friday, March 27, We received word that Youngstown Tile would like to start the retile work this week. That didn’t leave much time for notification of our members, but we did the best we could in that short time. Showers in this area will be unavailable for a period of 6-8 weeks while this work is being done. Yes, the steam room will be open in case you were worried! Showers will also be available in the boys locker room during this time. The project will replace all the stained, chipped tile with fresh tile over top of a water proofing membrane that will eliminate the seepage of water into the steam room area as well as in the locker room itself under the sinks. A chemical and mechanical cleaning operation will take place on the tile under the sinks to remove the deposits that has created an unsightly appearance. When complete, this will no longer occur. Additionally, all of the shower bays will be available for use once the project is completed. Thank you for your patience!
“Scaling and deposits will be eliminated and each basin replaced with new tile.”
UPDATE – January 27, 2026